Enrgy engineers installing and connecting a small Aux Transformer at a gas peaking plant near Chester.
14 No Screw piles. 6 No with transition steel to support a 40ft package plant container and 4 no piles for 2 no ring beams to support transformers and oil bunds.
Electrical team 1st and 2nd fix of LV cabling to energise a sub station. 5 MW project near Leamington Spa.
Charlbury, Oxford, 5MW
Scope – Civils, Earthing, LV Electrical, HV cable install.
Exothermic welding 50mm copper tape and rods to form an earth nest around a gas generation plant at a site near to Blackpool.
Enrgy design and build precast block solution for the support of containerized package plant from 20-40ft in length for good ground conditions.
A Waterlogged cable basement under HV equipment had to be fixed. Enrgy’s D&B solution was to re-seal all incoming cables and provide a well point system below basement level with automatic pumping system. Since installation the basement has remained dry.
Enrgy providing contestable works to build a SPEN DNO base. HV ring main equipment will sit at the head of the “F” shape and a GRP enclosure will keep it all dry.
2MW Roof-mount for Large UK PLC electrical wholesale warehouse, Stoke on Trent.
Scope – AC Electrics (Inverter to PoC)
A truly unique project in Manchester – The CIS Tower. A 400kw solar panel cladded building 100m high. Inspection, test and fault find to ensure the 10 year old system was working as designed.
HV cable box within a transformer . Enrgy replaced HV cables, improved general cable support and re-terminated onto the bushings
Enrgy engineers having swapped HV equipment earlier are now re-connecting the HV terminations before energising
LV feeds on 1500Kva Transformer being rectified by a Enrgy Engineer.
Enrgy’s D&B gas peaking plant project with newly supplied HV switchgear taking pride of place .
Field engineer undertaking annual DC testing on a 32 way string combiner box. This 28MW site has 140 such boxes to test.
Screw piled base with ring beam to accept 40t packaged plant
Lorem ipsum
Supply and install a temporary transformer c/w with all LV and HV cabling . The existing transformer had developed a fault and long lead time replacement meant a temporary transformer was the way forward.
1st and 2nd fix including commissioning of MV electrical components on a 5MW ground mount near Edinburgh.
Enrgy’s Batwing 6010 rotary mower. Fast to deploy and ideal on hard to reach grounds maintenance projects
Screwed piles and transition steel to support a 15t containerized package plant solution above the flood plain in weak ground on a solar farm near Dorset.
Enrgy performing an annual survey check on the roof of FA Training headquarters for England football - St Georges
Trefoils of 240mm single core AC cable running from remote distribution boards back to a central substation on a 5MW solar farm near Edinburgh
HV and LV cabling installation at a 5MW project in North Wales