50b28bb2-d0bb-48bd-9b6b-4c5212e4248f.JPG

Enrgy engineers installing and connecting a small Aux Transformer at a gas peaking plant near Chester.

IMG_2897.JPG

14 No Screw piles. 6 No with transition steel to support a 40ft package plant container and 4 no piles for 2 no ring beams to support transformers and oil bunds. 

IMG_2273.JPG

Electrical team 1st and 2nd fix of LV cabling to energise a sub station. 5 MW project near Leamington Spa.

Aerial south site.jpg

Charlbury, Oxford, 5MW

Scope – Civils, Earthing, LV Electrical, HV cable install.

IMG_4080.JPG

Exothermic welding 50mm copper tape and rods to form an earth nest around a gas generation plant at a site near to Blackpool. 

IMG_2566.JPG

Enrgy design and build precast block solution for the support of containerized package plant from 20-40ft in length for good ground conditions.

Lodge - basement pumps.JPG

A Waterlogged cable basement under HV equipment had to be fixed. Enrgy’s D&B solution was to re-seal all incoming cables and provide a well point system below basement level with automatic pumping system. Since installation the basement has remained dry.

Hawarden - DNO slab.JPG

Enrgy providing contestable works to build a SPEN DNO base. HV ring main equipment will sit at the head of the “F” shape and a GRP enclosure will keep it all dry.

IMG_3647.JPG

2MW Roof-mount for Large UK PLC electrical wholesale warehouse, Stoke on Trent.

Scope – AC Electrics (Inverter to PoC)

IMG_4187.JPG

A truly unique project in Manchester – The CIS Tower. A 400kw solar panel cladded building 100m high. Inspection, test and fault find to ensure the 10 year old system was working as designed.

Tx - recable.jpg

HV cable box within a transformer . Enrgy replaced HV cables, improved general cable support and re-terminated onto the bushings

Chalgrove - HV swap.jpg

Enrgy engineers having swapped HV equipment earlier are now re-connecting the HV terminations before energising

TX recable 2.jpg

LV feeds on 1500Kva Transformer being rectified by a Enrgy Engineer.

Hawarden - HV Gear.JPG

Enrgy’s D&B gas peaking plant project with newly supplied HV switchgear taking pride of place .

20170922_102019.jpg

Field engineer undertaking annual DC testing on a 32 way string combiner box. This 28MW site has 140 such boxes to test.

Hawarden - Pile and Frame.JPG

Screw piled base with ring beam to accept 40t packaged plant

Lorem ipsum

Stratton - Temp Tx.jpg

Supply and install a temporary transformer c/w with all LV and HV cabling . The existing transformer had developed a fault and long lead time replacement meant a temporary transformer was the way forward.

IMG_6151 (1).JPG

1st and 2nd fix including commissioning of MV electrical components on a 5MW ground mount near Edinburgh.

Photo 06-12-2016 15 43 24.jpg

Enrgy’s Batwing 6010 rotary mower. Fast to deploy and ideal on hard to reach grounds maintenance projects

IMG_4569.JPG

Screwed piles and transition steel to support a 15t containerized package plant solution above the flood plain in weak ground on a solar farm near Dorset.

St George - annual.jpg

Enrgy performing an annual survey check on the roof of FA Training headquarters for England football - St Georges

IMG_5944.JPG

Trefoils of 240mm single core AC cable running from remote distribution boards back to a central substation on a 5MW solar farm near Edinburgh

IMG_1578.JPG

HV and LV cabling installation at a 5MW project in North Wales